For factories that have wastewater treatment systems, they must have installation tools as required by law. There are criteria set forth in the regulations, which according to the rules must comply with the Ministry of Industry's announcement requiring factories to install special equipment or additional devices for wastewater treatment systems, B.E. 2547. SCMA has summarized this as follows:
Summary of the Installation Requirements for Special Equipment and Additional Devices, B.E. 2547

Factories listed in the Ministerial Regulation (B.E. 2535) that discharge wastewater as follows:
- Discharge volume exceeding 10,000 cubic meters per day
- Discharge volume between 3,000 to 10,000 cubic meters per day or have a BOD load (Influent BOD Load) of at least 4,000 kilograms per day
Must install equipment, special tools and additional devices, except for factories that do not discharge wastewater or those that treat wastewater in a central waste treatment plant (Central Waste Treatment Plant), which are exempt from installation.
- Discharge volume between 1,000 to less than 3,000 cubic meters per day
- Discharge volume between 500 to less than 1,000 cubic meters per day
Must have a wastewater treatment system and install equipment, special tools and additional devices, along with reporting the discharge of wastewater from the factory into the computer network system of the Department of Industrial Works.

Special tools or equipment and additional tools or equipment that must be installed
- Install a flow meter for wastewater discharge from the factory and an electricity usage meter for the sewage treatment system. These meters must continuously provide electrical signals to feed into the factory's computer system for data recording and continuous retrospective display.
- A Biochemical Oxygen Demand (BOD) or Chemical Oxygen Demand (COD) measuring device for wastewater that can continuously provide electrical signals. Some factories may need to install both types of devices, which must be approved by the Department of Industrial Works.
Requirements for signal-changing equipment used in installation
- Must have an alarm system when measurement values exceed limits.
- Can send signals to external receiving points prepared by the Department of Industrial Works.
- Can be connected and used with the Department of Industrial Works' computer network system.
- Can be controlled remotely from a remote control system.

This is the summary provided by SCMA. If you want to read the full version, you can access it at the Department of Industrial Works. For those factories looking for measuring tools and equipment for water flow measurement or various types of Flow Meter that can be used in a variety of factory settings, SCMA offers products from many leading brands along with experienced staff to assist you from installation through efficient use.
Reference: Department of Industrial Works